Polyethylene pipes replace concrete in power station's cooling water intake

Sponsored by

FOS-SUR-MER, France -- Alstom has now used polyethylene piping instead of concrete in a power station's cooling water intake for the first time. The advantages of polyethylene piping are that it is easy to install on the sea floor and has a life expectancy of at least 50 years in salt water compared to about -25 years for certain concrete pipes. The gas-powered combined cycle power plant was built in Fos-sur-Mer in southern France by CyCoFos, a power company that is a subsidiary of Gaz de France.

The pipe used was KWH Pipe's Weholite, one of the few polyethylene pipes in the world that can be made in dimensions of more than two meters. What makes the pipe unique is that it has a hollow profile wall that can be filled with concrete to weight it down. The piping is practically maintenance-free since all joints are welded and polyethylene does not corrode in salt water.

These qualities were factors behind the decision to bring the cooling water into the power station through polyethylene pipelines instead of using pipes of less advanced materials.

"Normally, external weights are used to weigh down polyethylene pipes, but it isn't practical when we're talking about pipes with diameters of two to three meters that are going to be buried under the sea floor for safety reasons", says Christian Vestman, project manager at KWH Pipe. "By using non-hardening cement mortar, the pipe retains its built-in flexibility, which means it can withstand different load situations on the sea floor better than rigid pipes."

Easy installation
Stephane Delaplace, who works for Alstom's subcontractor Entreprise Jean Negri & Fils, says it was no trouble to install the polyethylene piping:

"The job involved four parallel pipe sections of about 70 meters each. The piping was welded together in advance on land and transported as a whole to the installation location. They were then filled with water and sunk into the pre-dredged channels on the sea floor. Finally, the piping was covered with sand and rocks so the sea floor looked natural again."

Constructing piping with short concrete pipe sections that are connected with sleeve couplings on the sea floor requires significantly more diving, which is an expensive operation.

"The actual underwater work took less than a day per pipeline", says Delaplace. "There is also no risk of leakage in the piping, which is a risk with sleeve couplings."

###

Sponsored by

TODAY'S HEADLINES

MED desalination expansion worth $120m awarded in Saudi

A US$120 million contract has been awarded by the Saline Water Conversion Corporation (SWCC) for the expansion of the Shuaiba Phase 2 desalination plant in Saudi Arabia...

American Water enters exclusive U.S. partnership with ino3W water technology accelerator

American Water announced that it has entered an exclusive U.S. partnership with ino3W, a global water technology validation accelerator.

DOE now accepting applications for $3.6M Hydroelectric Production Incentive Program

The U.S. Department of Energy has announced an incentive program for developers adding hydroelectric power generating capabilities to existing non-powered dams throughout the United States.

Water reuse technology helps PA power plant save 1.3 MGD of drinking water

Covanta's Delaware Valley energy-from-waste facility in Chester, Pa., has saved 1.3 million gallons per day from local water supplies by installing advanced water reuse technology from GE in the power plant's cooling tower.