Watershed restoration project in Everglades to resume

March 31, 2010
WEST PALM BEACH, FL, March 31, 2010 -- A judge has renewed the potential for Everglades restoration to become a reality by ordering the South Florida Water Management District to resume and complete construction of the A-1 reservoir...

WEST PALM BEACH, FL, March 31, 2010 -- Federal District Court Judge Federico Moreno today renewed the potential for Everglades restoration to become a reality by ordering the South Florida Water Management District to resume and complete construction of the A-1 reservoir, one of 68 projects authorized under the Comprehensive Everglades Restoration Plan (CERP).

Construction commenced on the massive 16,700-acre reservoir, the largest in the world, in 2006 as part of former Gov. Jeb Bush's successful Acceler8 program. Gov. Charlie Crist worked with the District to halt construction of the reservoir in 2008 in order to divert the funds to his proposed purchase of U.S. Sugar's lands.

The District had already spent nearly $300 million when the project was abruptly stopped.

"Thankfully, we have an independent judiciary that is willing to do the right thing and is not blinded by politics," said Gaston Cantens, vice president of Florida Crystals.

Florida Crystals has opposed Gov. Crist's U.S. Sugar deal because of the negative impact it has had -- and would continue to have -- on the District's financial ability to construct Everglades projects. In fact, to date, not a single authorized CERP project has ever been completed. The U.S. Sugar acquisition further hinders the Everglades and delays preservation efforts.

In his order, Judge Moreno agreed, stating: "Although the partial sugar land acquisition may be in the best interest of the Everglades in the very distant future, the [Miccosukee] Tribe's environmental suffering is immediate."

Florida Crystals commends the Miccosukee Tribe for their efforts on behalf of the Everglades and pledges to continue working toward successful Everglades preservation.

###

Sponsored Recommendations

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track

Automated Fresh Water Treatment

March 15, 2024
SCADA, Automation and Control for Efficient and Compliant Operations

Digital Transformation Enables Smart Water

March 15, 2024
During this webinar we will discuss factors driving the transformation to digital water, water industry trends, followed by a summary of solutions (products & services) available...

Automation for Water Treatment and Distribution Systems

Jan. 31, 2024
Dependable, Flexible Control Solutions to Maximize Productivity