Reservoir contractor, Tampa Bay Water agree on settlement

Sponsored by

CLEARWATER, FL, Feb. 22, 2011 -- Tampa Bay Water's board of directors today approved a settlement agreement with the Regional Reservoir's general contractor, Barnard Construction. Under the terms of the agreement, Barnard Construction and its subcontractor McDonald Construction Corp., will pay Tampa Bay Water $750,000 before trial; Barnard remains liable for up to $5 million depending on the outcome of the trial scheduled for July 2011.

The settlement reflects the overwhelming evidence gathered in the discovery process that shows that the soil-cement cracking at the reservoir was caused by the engineer's bad design and not by any deficiencies in the actual construction of the embankment.

"This agreement allows Tampa Bay Water to focus its litigation efforts on HDR Engineering, and keeps Barnard Construction in the case to defend itself and its work against HDR's claim that construction is responsible for the cracking," said Richard A. Harrison, Tampa Bay Water's counsel for the litigation. "Barnard and its earthworks subcontractor are the people in the best position to defend their own work and we expect they will do so vigorously and persuasively."

Tampa Bay Water filed the lawsuit in federal court in December 2008 against HDR Engineering Inc., the reservoir's design engineer; Barnard Construction, the contractor; and CDG, which provided construction management. The board reached a settlement agreement with CDG in October 2010. The legal case against HDR Engineering Inc. continues, with a trial scheduled for this summer.

"Tampa Bay Water will continue to pursue the litigation against the design engineer, HDR Engineering," affirms Tampa Bay Water General Manager Jerry Seeber. "The evidence and testimony gathered through the discovery process demonstrates that HDR's defective design is the cause of the cracking at the reservoir. We will hold the engineer accountable for its failures on this important public project."

As the legal case progresses, Tampa Bay Water is procuring a permanent fix for the soil cement cracking so the reservoir can function as intended for the long-term.

For more information, go to or call Tampa Bay Water at 727.796.2355.

Tampa Bay Water provides wholesale water to the public utility systems of Hillsborough, Pasco and Pinellas counties as well as the cities of New Port Richey, St. Petersburg and Tampa.


Sponsored by

Did You Like this Article? Get All the Water Industry News Delivered to Your Inbox or Mailbox

Subscribe to one of our magazines or email newsletters today at no cost and receive the latest information.


Central Valley groundwater levels reach historic lows; land subsidence intensifies

According to a new article published by the U.S. Geological Survey, groundwater levels in many wells across California's Central Valley are at or below historical low levels this year.

Philippines’ water market ripe for European participation, finds new report

Private sector water participation will increase in the Philippines up until 2020 with nine projects lined up...

GE’s Water boosts UF membrane offering with IMT acquisition

GE has acquired Netherlands-based membrane manufacturer IMT Solutions for an undisclosed sum...

WaterTAP features third-annual World Water-Tech Summit in Toronto

This week, more than 50 of the world's leading water experts will be in Toronto, Ontario, for the third annual World Water-Tech North America summit, being held October 6-8. The Water Technology Acceleration Project is the event's key partner in North America.




© 2015. PennWell Corporation. All Rights Reserved. PRIVACY POLICY | TERMS AND CONDITIONS