Tampa Bay Water selects firm for reservoir renovation project, will add 3 billion gallons of water storage

Sponsored by

CLEARWATER, FL, June 20, 2011 -- Tampa Bay Water has selected design-builder Kiewit Infrastructure Group to renovate the regional reservoir and increase the facility's storage by 3 billion gallons. Contract negotiations are expected to be complete by August 1.

The main driver for the reservoir project is to repair cracks in the in the facility's soil-cement erosion control lining, which began appearing in 2006.

"We believe the Kiewit proposal will address the underlying causes of the reservoir's soil cement cracking and restore full functionality," said Tampa Bay Water General Manager Jerry Seeber.

Kiewit's $162.4 million solution removes and reclaims the reservoir's existing flat-plate soil cement and soil wedge; removes the geomembrane; and adds embankment fill, a drainage system, a new geomembrane and stair-step soil cement around the entire interior face.

About $42 million of the proposal is devoted to increasing the reservoir's capacity.

Seeber said the increased storage "puts the regional utility in a better position to meet demand when the economy recovers and when the next drought occurs." Adding capacity during construction is more affordable than building a second reservoir or expanding this reservoir later, he said.

To add storage to the 15.5-billion gallon facility, Kiewit will increase the height of the embankment by using a stair-step soil-cement structure on both the sides of the embankment. Stair-step soil cement is a robust facing that can withstand frequent drain and fill cycles, wave action and storms.

A concrete wave-wall will be anchored on the interior side of the crest.

Tampa Bay Water estimates that project could mean a water cost increase of $1.20 per household, per month.

Tampa Bay Water expects to offset the cost of the renovations with recovery in the lawsuit against reservoir designer HDR Engineering. In December 2008, the utility filed a complaint against HDR; Barnard Construction, the contractor; and CDG, which provided construction management. Tampa Bay Water has reached settlements with both CDG and Barnard Construction. The legal case against HDR Engineering is scheduled for trial in July 2011.

##

Sponsored by

TODAY'S HEADLINES

Major CA groundwater storage project for drought, emergencies underway

A groundwater supply project by the San Francisco Public Utilities Commission that will provide a water "savings account" to protect against future drought and earthquakes in the Bay Area has completed environmental review and is moving forward to construction later this year.

Study estimates total mass of oil reaching Gulf shore in wake of Deepwater Horizon spill

A research team from the New Jersey Institute of Technology has estimated the total mass of oil that reached the Gulf of Mexico shore in the wake of the BP Deepwater Horizon spill, which occurred in April of 2010.

Gas leaks from faulty fracking wells linked to groundwater contamination, finds study

A new study has found that improved construction standards for cement well linings and casings at hydraulic fracturing sites is the likely source of most natural gas contamination in drinking water wells associated with fracking.

New book implores industry leaders to reexamine relationship with water

The Water Innovation Project released a new water book for preorder, titled "Damned If We Don't! Ideas for accelerating change around water," focused on water-related issues and stories from authors representing ideas of better managing the industry's relationship with water.

FOLLOW US ON SOCIAL MEDIA