DANVILLE, VA, July 16, 2014 -- Duke Energy, the largest electric power holding company in the U.S., recently completed major cleanup work of spilled coal ash along the Dan River just upstream of the Schoolfield Dam in Danville, Va.

On Feb. 2, 2014, Duke Energy spilled an estimated 30,000 to 39,000 tons of coal ash into the Dan River between the city of Eden, N.C., and Danville, Va., polluting the waterway and potentially threatening public health.

The spill was caused by a break in a 48-inch stormwater pipe located underneath Duke's unlined 27-acre, 155-million-gallon ash pond, ultimately draining an estimated 24 to 27 million gallons of contaminated water into the Dan River. The occurrence signified the third largest coal ash spill in U.S. history.

Since the cleanup operation began on May 6, approximately 2,500 tons of coal ash and river sediment have been removed from this location. Crews and equipment were staged at Abreu-Grogan Park in Danville for the past three months.

The company also previously completed removal of ash and sediment from water treatment facilities in Danville and South Boston, as well as from locations in the river at the Dan River Steam Station and Town Creek, two miles downstream from the plant. More than 500 tons of coal ash and river sediment has been removed from these areas.

The company expects equipment demobilization and restoration activities in the park to continue for the next two weeks, with plans to return the park to the public in late July. Duke Energy is working with the city of Danville to identify future opportunities for additional enhancements at the park, such as improved river and fishing access areas.

All ash removal operations have been under the direction of the EPA and conducted in conjunction with state and other federal agencies. Based on the EPA's criteria, there currently are no additional deposits to be removed from the river. Duke Energy, EPA and other agencies will continue monitoring and will remove additional coal ash and sediment deposits if identified and deemed necessary.

Duke Energy conducted nearly 2,000 surface and drinking water samples in the Dan River. Drinking water quality has remained safe since the spill, and surface water quality returned to normal conditions within days of the event. As a result, the EPA, in conjunction with other federal and state agencies, has concluded that enhanced drinking and river water quality sampling is no longer necessary along the river. Sediment, fish tissue and other biological sampling will continue until further notice.

See also:

"Duke Energy NC coal ash spill signifies third largest in U.S. history"

###

Sponsored by

TODAY'S HEADLINES

De Nora completes acquisition of Severn Trent's Water Purification group

De Nora has announced the completion of the acquisition of Severn Trent Services' Water Purification group. The new business title, called De Nora Water Technologies, will be focused on delivering sustainable and innovative water and wastewater technologies.

USACE signs partnership agreement with MS city mayors for water-related projects

The U.S. Army Corps of Engineers - Vicksburg District of Mississippi recently announced that it has entered into a Partnership Project Agreement with mayors of several communities throughout the state.

First large-scale RO system in FL to use ozone for treating H2S in RO permeate

The city of Clearwater, Fla., recently completed its new brackish reverse osmosis (RO) water treatment plant No. 2, which serves as the first large-scale RO municipal system in the state of Florida to use ozone to treat H2S in RO permeate.

FCC Aqualia secures O&M contract for two largest WWTPs in Mecca, Saudi Arabia

FCC Aqualia, in association with lkhorayef Water and Power Company of Saudi Arabia, recently announced that is has secured a contract comprising the operation and maintenance of the two largest wastewater treatment plants in the city of Mecca.

FOLLOW US ON SOCIAL MEDIA

  

 


© 2015. PennWell Corporation. All Rights Reserved. PRIVACY POLICY | TERMS AND CONDITIONS