Stormwater Detention System Helps Dealership Manage Runoff and Build Sales

June 18, 2015
A new Faulkner Automotive car dealership in Mechanicsburg, Pa., found a way to maximize sales by increasing its display area while also being able to meet environmental requirements. For stormwater management, detention systems were constructed under the sales display areas using large diameter, corrugated high-density polyethylene (HDPE) pipe. The systems are designed to reduce flow for the entire 14.5-acre site, which includes four 20,000-square-foot buildings.
Stormwater detention systems were constructed under the sales display areas using large diameter, corrugated HDPE pipe.

A new Faulkner Automotive car dealership in Mechanicsburg, Pa., found a way to maximize sales by increasing its display area while also being able to meet environmental requirements. For stormwater management, detention systems were constructed under the sales display areas using large diameter, corrugated high-density polyethylene (HDPE) pipe.

"Instead of proposing a traditional open-pond detention/retention system, two large underground detention systems were installed to maximize usable area on the property for vehicle sales display," said Todd Wilson, project manager for Alpha Consulting Engineers, Inc., and designer of the systems.

"The property is underlain with limestone," Wilson explained. This meant that rather than meeting the water infiltration requirement of Pennsylvania's Control Guideline 1 (CG1), the stormwater facilities were designed to comply with CG2 requirements and included more extensive water quality best management practices (BMPs). The proposed BMPs would control the peak flows and also meet the Environmental Protection Agency's (EPA) retention water quality facilities ordinance requirements. "Also, we wanted to come up with the most cost-effective design that we could," Wilson said.

According to the Plastics Pipe Institute, Inc. (PPI), the major trade association representing all segments of the plastic pipe industry, there are ever-increasing needs for proper stormwater management. "EPA's Storm Water Management Model (SWMM) was first developed in 1971 and has since undergone several major upgrades," said Daniel Currence, director of engineering, CPPA Division, PPI. "It continues to be widely used throughout the world for planning, analysis and design related to stormwater runoff, combined sewers, sanitary sewers, and other drainage systems in urban areas, with many applications in non-urban areas as well."

Stormwater management has traditionally required that there be no increase in the rate of runoff from development as compared to the rate of runoff before the development. This is for storms ranging from the 2-year/24-hour event to the 100-year/24-hour event. "Now, there is also the need to meet other federal, state and local environmental protection requirements including the trapping and controlling of total suspended solids," said Currence. "This project required the system be designed to manage the 100-year flow rate of 44.5 CFS."

The detention systems, located in the front and back of the property, were installed by JVH Excavating. The overall excavation area measured 158 x 246 feet for the 48-inch system and 119 x 206 feet for the 36-inch system, with 3 to 4 feet of cover to finished grade. For Retention System One, with capacity gauged at 0.75 acre-feet of water, 4,800 linear feet of 36-inch-diameter corrugated HDPE pipe was used. Detention System Two has 5,640 linear feet of 48-inch diameter HDPE pipe to meet the capacity of 1.5 acre-feet of water. The HDPE pipe and custom fabricated manifolds were manufactured by Lane Enterprises, Inc., a member company of PPI, at its production plant in Shippensburg, Pa.

The detention systems are designed to reduce flow for the entire 14.5-acre site, which includes four 20,000-square-foot buildings.

"Even with the extensive amount of pipe -- 24 rows of HDPE pipe -- and manifolds, it was quick to install," said Wilson. "From the beginning of installation, it was completed in about a week." Wilson explained that the systems are designed to reduce flow for the entire 14.5-acre site, which includes four 20,000-square-foot buildings. Peak flows are controlled by means of a stainless steel orifice plate installed within a junction box directly down-slope of the detention facility. From the detention system, water is directed into the existing public storm sewer service.

Eventually, there will be a total of eight new Faulkner Automobile dealerships located in this area southeast of Harrisburg. The next dealership is being built directly across the street in 2015 and will have four HDPE detention systems constructed from a total of 6,300 24-inch-diameter HDPE pipe and fabricated manifolds.

About the Author: The Plastics Pipe Institute Inc. (PPI) is the major trade association representing all segments of the plastic pipe industry and is dedicated to promoting plastics as the material of choice for pipe applications. The organization is the premier technical, engineering and industry knowledge resource, publishing data for use in development and design of plastic pipe systems. Additionally, PPI collaborates with industry organizations that set standards for manufacturing practices and installation methods. To learn more, visit www.plasticpipe.org.

Sponsored Recommendations

Meet the future of MV switchgear

SureSeT new-generation metal-clad. Smarter. Smaller. Stronger.

A digital circuit breaker built for the future

EvoPacT medium voltage digital vacuum circuit breaker

The New Generation of Intelligent MV Switchgear

Step into the future of electrical infrastructure with Intelligent MV Switchgear - where traditional equipment becomes smart, providing real-time data on critical components like...

Switchgear goes digital with SureSeT

Discover what you can do with Square D natively digital MV metal-clad switchgear.