A PC surveyor is shown on the Yuma display. The surveyor is seen from the total station mounted on a bracket on the shaft wall (above the red ladder.)
Adopting New Technologies
The company’s effort to integrate BIM with field work encountered some challenges, noted Ron Ellison, PC chief field engineer. “The big challenge for us was how to get this 3D model into the field.”
New generations of workers are readily adopting these approaches, but Ellison said that even seasoned workers recognize the value of 3D models in the field. It enables them to visualize the components of the project they are working on and see the relationship to yet-to-be-constructed aspects. Prior to concrete pours, PC workers can verify that forms and rebar are positioned correctly. Construction workers use the models to install MEP and other components.
Ellison develops site information and constructible models from design documents and sends them to the field for layout, excavation and grading. “We’re seeing 30 percent savings, maybe more, compared to what I call the old-school 2D way,” Ellison said. “Having a model means it’s set up, checked and ready to go.”
Preventing Problems
The ability to measure and plan in detail delivered big benefits. One example is the installation of a large header pipe needed to deliver water to the pumping equipment. The steel header is 13 feet (4 m) in diameter and runs the width of the shaft. PC rented a special crane to handle the pipe. “We had just two days to put everything together,” Torres said. “We worked with zero tolerance, because the pipe is so big and heavy that if we had needed to move it then it would probably have broken all the anchor bolts, which would have been a disastrous setback. Everything was thoroughly planned, checked and re-checked.” The rigorous measurement and checking enabled installation to move according to plan.
“That’s our biggest benefit: to catch and eliminate mistakes in the office before they get to the field,” Ellison said.
Harraka pointed to recent graduates emerging from trade schools and colleges as an enabling force for BIM and virtual construction technologies. As we go forward there’s going to be more tech-savvy people. This can do nothing but grow.” WW
John Stenmark is a writer and consultant who has more than two decades experience working in the architecture/engineering/construction and technical industries.
Circle No. 241 on Reader Service Card