SAN DIEGO, Calif., March 5, 2002 - The San Diego County Water Authority has chosen the management consulting and engineering firm R. W. Beck Inc. as the prime consultant to provide construction management services for a water pipeline project in San Diego.
The project, Moreno Lakeside Pipeline, encompasses approximately five miles of 54- to 60-inch diameter pipelines - including two tunnel segments - operated by the San Diego County Water Authority on the east side of the Southern California city.
The project is scheduled to begin in June 2002 and should be complete by September 2004.
"The pipeline project will provide water to the Levy Water Treatment Plant operated by the Helix Water District (a member agency of the San Diego County Water Authority), which serves customers in an area to the east of the City of San Diego," according to project manager Chris Dull of R. W. Beck's San Diego office.
For 60 years, R. W. Beck has been taking the lead to guide utilities across the nation and various parts of the world as they chart a course for the future.
Besides San Diego, the firm has California offices in Sacramento and Laguna Hills.
Founded in 1942, R.W. Beck is a management consulting and engineering firm with 22 offices that provides services to the public and private sectors in the areas of energy, water resources, solid waste and telecommunications.