Affholder wins $44M contract for Sacramento sewer tunnels

Aug. 16, 2004
The Sacramento Regional County Sanitation District has awarded Affholder Inc. a contract to bore tunnels at two points under the Sacramento River, part of a new 19-mile sewer line to transport wastewater from west Sacramento and the rapidly growing north county...

CHESTERFIELD, MO, Aug. 10, 2004 -- The Sacramento Regional County Sanitation District has awarded Affholder Inc. a $44 million contract to bore tunnels at two points under the Sacramento River.

The tunnels are part of the new Lower Northwest Interceptor, a 19-mile sewer line that will transport wastewater from West Sacramento and rapidly growing north Sacramento County to the Sacramento Regional Wastewater Treatment Plant near Elk Grove, California. The northern river crossing will be located east of the I-80 Interstate Bridge; the southern crossing will be north of Sacramento's Freeport Bridge.

"When the District looked at the region's sewer needs for the next 50 years, it was clear that significant growth would occur in the northern part of Sacramento County," explains Bill Moler, lead tunnel engineer for The Lower Northwest Interceptor Program. "This new interceptor is needed to support the previously planned general growth in that area."

When completed in 2006 the Lower Northwest Interceptor is expected to serve about 200,000 households and carry peak wet weather flows of up to 200 million gallons a day.

Affholder's contract calls for the company to begin each set of tunnels by excavating 25-foot by 150-foot access shafts on both sides of the river, where it will launch and receive its tunnel boring machines. Working from these shafts, workers will then bore tunnels, each about 15 feet in diameter and 2,000 feet in length, at each of the two crossings. During the excavation of the tunnel, Affholder will line each tunnel with a 13 ½-foot diameter precast concrete, watertight, segmental tunnel liner. Upon completion of the tunnels, twin steel pipes will be installed inside the tunnels as the sewer line.

The tunnels will connect on both sides of the river crossings with pipelines that are being constructed under separate construction contracts. "It will take a work crew of 45 to 50 persons about two years to bore and line the tunnels," according to Bob Stier, area manager for Affholder. Work on the project is expected to begin in August and continue through the summer of 2006.

Affholder Inc., a subsidiary of Insituform Technologies Inc., uses tunneling methods to perform trenchless installations of new pipelines throughout North America.

###

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track