A section of Hobas pipe being installed. Click here to enlarge imageA direct bury project like this one needed a simple slip joint. Once the line was installed, the pipe was tested. The air test held so well that the team decided to plug the manholes and test up to 2,000 linear feet at a time. The entire line was pressure-tested to six psi for two hours without a single leak or pressure drop.
Lowest Total Cost
HDR developed capital costs for the sewer alignment alternatives. Alternative two provided the lowest project cost to meet the current need, however, this would not have delivered the lowest life-cycle cost. To determine the lowest life cycle for the project, LWWS believed it was necessary to use a projected growth rate, projected flows and an estimate of the present value of both alternatives. The calculations, based on present values, showed that the gravi-force sewer option would have an overall saving of $300,000 compared with the force main option.
The project is now completed, and the complete construction cost was approximately $1.5 million. Savings resulted primarily from not having to install a new sewer 20 years down the road. Since major redevelopment will occur in this area for the next 10 years, the $300k is likely an understatement of total cost savings. The project was completed within the CIP budget the city set for the first sewer project, providing a 50-year solution for the cost of one project versus two planned projects.
Apparently, this is the first identified application for the gravi-force concept. The authors could not find other documented instances where a utility had designed specifically for this concept. Construction was begun in 2005 and completed within nine months and the sewer is operating successfully.
About the Authors:
Kent Prior, P.E., is a senior project manager based in HDR’s Lincoln office. Scott Aurit, P.E., is a project engineer based in HDR’s Omaha office. Brian Kramer, P.E., is an engineer with the city of Lincoln Wastewater System.