Click here to enlarge imageDesigned to achieve a consistent, desired level of chloramine residual throughout the entire tank, the RMS system was initially installed during the winter of 2000 at the four million gallon Nellie Gail Reservoir. No downtime was needed to put the system in place.
Operation of the system relies on a submersible pump installed through the roof of the tank and suspended about three feet from its floor, combined with an eductor nozzle on the pump effluent. Working together, these two components create a significant upflow of water, thoroughly mixing the tank's contents and eliminating thermal and residual stratification.
The system also includes free and total chlorine residual analyzers designed to measure chlorine levels throughout the tank. If either analyzer senses a deviation from setpoint, a dedicated PLC-based control calls for the injection of ammonia and/ or hypochlorite via conventional chemical metering pumps until proper chloramine residuals are restored. The circulation pump runs continuously, providing a fresh sample stream to the analyzer while continuing to blend the various flows in the reservoirs. The PLC-based control communicates all system operating parameters, residuals, etc., directly to the district's SCADA system where data is trended and analyzed.
Severn Trent also installed an on-site hypochlorite generator to produce 0.8 percent sodium hypochlorite at the Nellie Gail site, effectively eliminating the need for chemical transport and handling. Enough sodium hypochlorite solution is produced and stored to meet one or two day's requirements at maximum operating capacity.
Results
Results of the RMS system have proven significant. Improved mixing and real-time chlorine analysis have allowed the district to maintain a more homogenous water quality with consistent chlorine residuals throughout the tank.
The system also enables the reservoirs to be operated at higher levels, making more effective use of available capacity. When installed district wide, the RMS technology and capital equipment will provide the equivalent of three additional five million gallon reservoirs and one additional two million gallon storage tank, effectively eliminating the need to construct additional reservoirs, and saving substantial capital investment.
Because nitrification is no longer a problem, the new system also dramatically reduces the need for flushing. This does more than reduce labor and its associated costs; it also eliminates the public perception that the district is wasting water. This is also enhanced by the closed loop, reagentless nature of the analysis process, since all analyzed samples are returned to the tank for reuse.
Conclusion
Thanks to the success of the six-month pilot program, the ClorTec Reservoir Management System is now being adopted throughout the Moulton Niguel District. Phase I includes installations at eight sites involving 12 reservoirs. The remainder of the district will be converted during Phase II. All installations will be turn-key projects, and will include on-site chlorine generation, ammonia refrigeration and storage, PLC-based control systems with operator interface, free-chlorine residual analyzers, total chlorine residual analyzers, chemical metering pumps, submersible pumps and eductor assemblies, recorders, and associated valves and tank level controls.
About the Author: