Task Force advances more than $230M in coastal restoration projects

Jan. 20, 2010
BATON ROUGE, LA, Jan. 20, 2010 -- Today, Governor Bobby Jindal announced that the Coastal Wetlands Planning, Protection and Restoration Task Force (CWPPRA) approved nine projects for design and construction...

• The Task Force's approval represents the largest CWPPRA investment in Louisiana's history

BATON ROUGE, LA, Jan. 20, 2010 -- Today, Governor Bobby Jindal announced that the Coastal Wetlands Planning, Protection and Restoration Task Force (CWPPRA) approved nine projects for design and construction that will ultimately benefit more than 3,100 acres of Louisiana's fragile coastal wetlands, barrier islands and beaches. The task force approved the projects at its meeting today in New Orleans.

The projects, which are spread across seven coastal parishes including Plaquemines, Jefferson, St. Charles, Lafourche, Terrebonne, Vermilion and Cameron, represent a total of more than $230 million in state and federal funds. This represents the largest CWPPRA investment in coastal restoration projects in Louisiana's history. Specifically, over $100 million in funds were approved for construction of five restoration projects and nearly $11 million in engineering and design funds will advance four additional restoration efforts. The estimated $120 million construction cost of the design projects are expected to be funded in future years.

Governor Jindal said, "These projects are a critical part of our overall effort to restore and protect Louisiana's coastal ecosystems and communities. We've invested a record $660 million in coastal restoration and hurricane and flood protection projects during the past two years, and CWPPRA projects will remain a key element as we continue to make larger, historic investments in coastal restoration projects."

Projects Approved For Construction:

• Cameron-Creole Freshwater Introduction, Vegetative Plantings: Will restore 200 acres of hurricane-impacted marsh in Cameron Parish at a cost of $1,147,096. The restored marsh will stabilize the area that will benefit from a freshwater introduction component of the project.

• Barataria Basin Landbridge: Will protect three miles of shoreline along Bayou Perot and Little Lake in Jefferson Parish which is experiencing up to 15 feet of erosion per year. The project will protect 107 acres of marsh at a total cost of $20,489,664.

• West Belle Pass Barrier Headland Restoration: Will restore the barrier headland function of this area that will provide a first line of defense to Port Fourchon and Lafourche and Terrebonne Parishes. The project will benefit 305 acres at a total cost of $42,250,417.

• South Grand Chenier Hydrologic Restoration: Will introduce freshwater, sediment, and nutrients into newly created marsh in Cameron Parish, reducing salinities and increasing vegetative coverage. This project will benefit 453 acres at a total cost of $29,046,128.

• GIWW Bank Restoration of Critical Areas in Terrebonne: Will restore critical lengths of deteriorated banks of the Gulf Intracoastal Water Way, providing protection to the largest floating marsh complex in Coastal Louisiana. This project will benefit 65 acres at a total cost of $13,022,246.

Projects Approved For Design:

• Lost Lake Marsh Creation and Hydrologic Restoration: Will restore 749 acres of marsh along the shorelines of Bayou Decade and Lake Pagie in Terrebonne Parish at a cost of $22,943,866. Several water control structures will also be replaced to allow more freshwater and sediment input into the project area.

• Freshwater Bayou Marsh Creation: Will restore of 279 acres of marsh along the western shoreline of Freshwater Bayou in Vermilion Parish at a total cost of $25,523,755. It will help to protect the Mermentau Basin from saltwater intrusion.

• LaBranche East Marsh Creation: Will restore 715 acres of marsh along the I-10 hurricane evacuation corridor in St. Charles Parish using sediment from Lake Pontchartrain, at a total cost of $32,323,291.

• Cheniere Ronquille Barrier Island Restoration: Will restore 234 acres of barrier island habitat in Plaquemines Parish at a total cost of $43,828,285. The project will restore the island's function as a first line of defense against hurricane storm surges.

"CWPPRA has done a remarkable job of putting projects on the ground relatively quickly, including two barrier island restorations and two of the largest marsh creation projects ever built in our state in 2009 alone," said Coastal Protection and Restoration Chairman Garret Graves, who represents the state on the CWPPRA Task Force. "These nine projects are a key part of an overall $17 billion ongoing effort to restore and protect coastal Louisiana. With the restoration projects underway today because of state investments, we're projected to have the lowest rate of land loss since the 1930's."

In other business, the CWPPRA Task Force voted to close the West Bay Sediment Diversion in lower Plaquemines Parish during the next low water period on the Mississippi River. The diversion, which was built by the Army Corps of Engineers to divert water from the Mississippi River into adjacent coastal areas, has conveyed as much as 50,000 cubic feet per second of water into shallow water areas west of the river. The project's success and impacts have been the source of much scrutiny in recent years.

Corps officials claimed that the West Bay diversion was inducing shoaling, or causing the build up of sediment in navigable and anchorage areas of the river. According to an agreement signed before the diversion's construction, funds from CWPPRA, intended to be used specifically for coastal restoration projects, would be used to dredge the anchorage area if it was determined that the diversion was causing the shoaling.

Studies conducted by state officials, and confirmed by the Corps in 2009, showed that only a fraction of the shoaling was being caused by the diversion. However, rather than bearing the cost of annual dredging the anchorage, the Task Force voted to develop a closure plan for the diversion.

"Closing this diversion is a real disappointment, but continuing to dedicate coastal restoration dollars to dredging projects is simply unsustainable. Until this induced shoaling issue is addressed by Washington, portions of our coastal program are going to keep hitting this brick wall" Graves said. "Until we resolve this policy issue and direct the proper resources needed to use the Mississippi River for both navigation and restoration, closing West Bay will accomplish nothing."

The Coastal Wetlands Planning, Protection and Restoration Task Force, or Breaux Act Task Force is a federal-state task force charged with carrying out small-scale restoration efforts in coastal Louisiana. The U.S. Army Corps of Engineers, National Oceanographic and Atmospheric Administration, U.S. Fish and Wildlife Service, Environmental Protection Agency, Natural Resources Conservation Service and the State of Louisiana are represented on the task force.

For additional information, please call Chris Macaluso in the Office of Coastal Activities at (225) 342-3968 or email at [email protected].

About LACPRA
The Coastal Protection and Restoration Authority's mandate is to develop, implement and enforce a comprehensive coastal protection and restoration master plan. For the first time in Louisiana's history, this single state authority will integrate coastal restoration and hurricane protection by marshaling the expertise and resources of the Louisiana Office of Coastal Protection and Restoration and other state agencies, to speak with one clear voice for the future of Louisiana's coast. Working with federal, state and local political subdivisions, including levee districts, the CPRA will work to establish a safe and sustainable coast that will protect our communities, the nation's critical energy infrastructure, and our bountiful natural resources for generations to come. The CPRA of Louisiana was established by Act 8 of the 1st Extraordinary Session of 2005. Web: www.lacpra.org

###

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track