Project Profile: Set Your Watch by the ADTs

Nov. 10, 2017

Developments around Vancouver, British Columbia, show no signs of slowing down. In fact, Vancouver, like much of the West Coast in the United States, remains a hotbed for real estate developers. Just south of Vancouver in Tsawwassen, crews are moving materials to make way for Phase 2 of the Aquilini Development Tsawwassen Shores project.

Kevin Clarke, vice president of civil and infrastructure for Aquilini Development and Construction, says that the Vancouver economy is “very hot” right now, like San Francisco and Seattle, and the company has developments going all over the greater Vancouver area, as far east as Chilliwack. The company does everything from high-rise towers in downtown Vancouver to single-family and multi-family urban developments. “Vancouver has been a hidden gem for a long time, and it’s really come into its own in the last 10 years,” Clarke says. “The economy is booming right now and hopefully it keeps going.”

Master everything from OSHA regulations, to high-tech safety equipment in this FREE Special Report: Construction Safety Topics That Can Save Lives. Download it now!

Clarke has five multi-year Aquilini Development projects in progress. One example is Tsawwassen Shores, a master planned community with single-family and multi-family homes conveniently located near Tsawwassen Mills, the Pacific Ocean, and downtown Vancouver. The 270-acre waterfront project is just south of Richmond and is being developed in multiple phases. Clarke says it won’t be fully finished until at least 2020 or 2021, and he says it is a joint venture with members of the Tsawwassen First Nation. Aquilini Development manages the project and does everything from the earthmoving work to the complete construction, sales, and closings of properties.

Aquilini Development is a division of Aquilini Investment Group, and until only a few years ago, hired out its civil construction needs to general contractors. Three years ago, Clarke joined the company and has helped grow a new construction entity to perform the work rather than hiring someone else. “Self-performing on the civil side of things is becoming a pretty common entity these days,” he says. “I’ve been doing it myself for other companies for a number of years now, and most developers are recognizing that there’s a lot of cost savings in doing it yourself.”

Add Grading & Excavation Contractor Weekly to  your newsletter preferences and keep up with the latest articles on grading and excavation: construction equipment, insurance, materials, safety, software, and trucks and trailers.    

Difficult Soil Conditions
A significant challenge with the project has been soil conditions at the job site. Clarke says the area was a dumping ground for a variety of non-hazardous materials, from diverse soils to gravel and rock. “Our biggest challenge with this particular site is the weather and soil. We need sunshine and we need wind because we can get it structurally compacted if we have the dryness in it,” explains Clarke. “If it’s got any moisture in it at all, it won’t compact. So this year has been a real struggle for us. We weren’t able to get going until three or four weeks ago because of the weather we’ve had on the West Coast.

“Last year, we were able to start late April because we had such a beautiful summer and wrapped it all up probably the end of October. The great thing about being on the ocean is the wind—it really helps draw the moisture out of it.”

Clarke says articulated dump trucks are the only feasible solution to move the material. The company purchased four Doosan DA30-5 articulated dump trucks from Westerra Equipment, the local Doosan construction equipment dealer in Vancouver. “It has to be articulated dump trucks. You couldn’t take regular highways trucks onto this jobsite—they would disappear,” he says. “The operators are working 10-hour days, minimum, if the weather’s good. We’ve got to go.”

Photos: Doosan
The DA30-5 on the move

Phase 2, where crews are working this summer, is a property just west of the Tsawwassen Mills shopping mall, not far from the Pacific Ocean and near the Tsawwassen main ferry terminal to Vancouver Island. “There’s a lot of preloading involved to compress the existing ground,” Clarke says. “Because it’s waterfront work, we’re very close to sea level, so it’s a lot of preload. We’re trying to be efficient in that aspect of the existing material we have, we continue to move from phase to phase. Part of that process is bringing it up to a floodplain elevation, so we structurally build up to that elevation and then preload it on top of that. The very first part of that was the movement of excess material from Phase 1 three years ago to the start of our Phase 2 site, and we’re now in our third year of that preload being moved.”

Each Doosan DA30-5 can carry up to 17.8-cubic-meters (23.3-cubic-yards) and can travel up to 34 miles per hour, making them an efficient means of accomplishing bulk earthmoving tasks. “Last year we moved probably close to 500,000-cubic-meters (653,975-cubic-yards) of material, and it’ll be approximately the same this year. We carried the material up to a third of a kilometer (0.5 miles) last year, and this year it will be a little shorter haul.”

Crawler excavators load the Doosan articulated dump trucks before they transport the materials to another area of the development. In addition to the excavators and trucks, Clarke says the company has several dozers onsite and a harrow with disks that’s used to help dry the material quicker, if necessary.

At the waterfront project in Tsawwassen, Aquilini Development site superintendent Mike Zsombor oversees the daily construction development. One aspect of the Doosan ADTs that Zsombor appreciates is the short turning radius. Even though you might think there’s ample room to turn around on a large site like this, Clarke says you’d be surprised.

“It’s a tight site, which may sound funny,” he says. “We try only to drive in certain areas at any given time, and also try to shorten up the haul. The quicker we can get turned around, the better off we are. It’s just part of earthmoving. Mike and the
operators are efficient at moving the dirt. It’s part of Mike’s process, especially at this site. Every site is different; but this particular site, the tight turning radius is critical.”

If the weather cooperates, the company hopes to work into fall again this year and finish the dirt work at Phase 2 of Tsawwassen Shores. From there, the company will eventually proceed with construction of the single-family and multi-family homes.

Mike Zsombor

Safety on the job site is paramount for Aquilini Development Group, and job site superintendent Mike Zsombor leads the way to ensure that operators are following the proper procedures. “Mike takes our operators through a general overview of the trucks,” says Kevin Clarke. “They have what they call ‘tailgate meetings’ every morning to discuss how they’re going to go about working—not just the truck drivers, but the excavator operators too. They talk about where they’re working and where they’re hauling material to.”

About the Author

Ryan Johnson

Des Moines journalist Ryan Johnson is a contributor of construction stories.

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track