A section of the existing sewer was removed to provide an insertion pit for the curved sections. Click here to enlarge imageThe contractor, Mladen Buntich Construction Co. of Sunland, CA, is a veteran installer of Hobas pipe. They have used it on a dozen previous jobs in the LA area. Their familiarity with the pipe enabled Buntich to reline many difficult reaches without incident.
"We knew using Hobas could save us money," said Lee Roesner, PE, project manager. He pointed out that the alternatives, which included other ways to accommodate traffic or bypass pumping, would be costly and perhaps impossible.
The pipe was installed at the rate of one pipe every five minutes in the 2,000-foot run. This rapid insertion rate was accomplished using an average pushing force of less than 40 tons, well below the 200-ton capacity of the pipe. In two separate areas, Buntich pushed 2,000 linear feet of pipe directly under several private homes.
The existing conditions and limited access prompted some creative installation methods. One inaccessible area of the deteriorated, existing sewer had a 100-foot long 90-degree radius curve. Buntich made several radius fittings with gasket sealed joints to structurally reline the sewer. These were pushed into the curved sections without disrupting flow.
"With our experience, we knew we could do this on site," said Roesner. "It is easy to do by cutting the pipe to length and laying back up."