Installing the PRO-RING™ Grade Adjustment System. |
The manhole adjustment system was of significant interest to NBC. This system was said to be faster, safer and more cost effective, with one person being able to complete an entire adjustment in just minutes. Using the PRO-RING system, a manhole repair site can be opened, reconstructed and closed in one day or less, reducing overall costs by as much as 20 to 30 percent. Since these grade rings weigh 95 percent less than concrete rings, they are much safer to use, minimizing the risk of worker injury.
On the day of the repair, crews and traffic control arrived and were set up by 7:30 a.m. The pavement was saw cut, and the manhole was excavated and ready to be reconstructed by about 8:50 a.m. The installation of the manhole adjustment system started at approximately 9 a.m., with some repair of the brick manhole using a high-early-strength repair mortar and then installing the adjustment rings and manhole frame casting.
The installation was completed by 9:20 a.m., and the excavation was backfilled, compacted and prepared for the asphalt patch. Unfortunately, the asphalt did not arrive to the site until approximately noon, but once on site it was placed and compacted with the entire repair being completed by 12:30 p.m.