Click here to enlarge imageIn early 1999, Port Hardy engaged EPCOR Water Services Ltd. to take over the entire water system on a design-build-operate basis, with a specific mandate to solve the water quality problem by constructing an appropriate treatment facility.
Various treatment options were evaluated including conventional and membrane technology and costs were estimated. From the evaluation, a DAF/filtration system was selected as the most appropriate and cost effective solution. The low-turbidity, tea-colored water has to be treated with a coagulant to form "floc" from the dissolved organic material and this floc tends to be fluffy and resistant to settling. Thus, the dissolved air flotation system, which is based upon myriads of microscopic bubbles buoying the floc upward, was considered to be a prime candidate.
Pacific Keystone of the Clearwater Group developed a conceptual design for the DAF/filtration plant and jointly conducted a pilot study with EPCOR. The four-week pilot study confirmed the efficacy of the process and further refined the design parameters of the full scale plant and its effectiveness was proven in the pilot testing.
With the results of the pilot study and a firm capital cost contract, EPCOR were free to proceed expeditiously; that is, they were not bound by rigid tendering procedures and similar time consuming routines. All capital cost construction items were negotiated using a "fast track" approach. Contracts were awarded for portions of the project even while others were still in the conceptual stage.
The main contract, for the treatment plant block, was let in late June 1999 as a design-build contract to Nason Contracting Group Ltd. as the General Contractor in association with Pacific Keystone as the process designer and equipment supplier.
The project benefited from the partnering approach adopted by EPCOR, the contractor and process designers with design review meetings held weekly. This hit-the-ground-running approach enabled the plant to be completed and producing treated water by late March of 2000 - less than eight months from design to commissioning.
All major tankage (DAF units and filters) were fabricated and assembled in marine grade aluminum (off-site at the Pacific Keystone manufacturing facility) and installed in Port Hardy upon a poured concrete slab. The entire plant was enclosed in a steel framed, metal clad, pre-fabricated building erected at the site. Thereafter all piping, electrical, instrumentation and building mechanical systems were installed. This use of pre-fabricated process equipment within a pre-engineered building considerably shortened the construction schedule.
The water treatment plant has a production capacity of 2.65 mgd and a hydraulic capacity of 3.3 mgd, the largest DAF drinking water plant in BC. Raw water entering the plant receives chemical addition of alum and soda ash and is then split among three DAF units. Each DAF unit incorporates flocculation (slow mixing) cells with variable speed turbine mixers followed by the flotation zone. The design surface loading on the DAF units is 4.5 US gpm/ft2.