A specially designed pontoon carried inspectors and video/audio equipment through the tunnel.
Click here to enlarge imageAn innovative video technology, the Aqua Zoom™ camera (by InfraMetrix, Wakefield, MA), a stationary camera with specialized lights and zooming capabilities, was used. Following verification by the Aqua Zoom camera that the general conditions were safe, core samples were also collected by lowering a man at the top, middle and bottom of each access shaft on each service lateral for laboratory analysis. At a total cost of less than $50,000, the preliminary inspection demonstrated sufficient structural integrity of the shafts and provided information to prospective bidders that no special safety measures would be needed – with an estimated savings to the city of more than a quarter of a million dollars to enter the access shaft.
Manned Inspection
Final inspection was conducted by an inspection contractor bid using plans and specifications prepared by Malcolm Pirnie. J.F. White Construction Company was awarded the inspection contract and chose to perform the work in two separate stages, with the total cost of inspection bid was $2,945,000. Stage I consisted of manned inspection of the shafts and laterals at the five locations; an inspector equipped with direct audio communication and fiber optic video recorder was lowered into each shaft using a basket support system and crane. Concrete core samples were taken throughout the shafts and laterals to assess the structural integrity, as requested by the Malcolm Pirnie engineer.
Stage II was the manned inspection of the tunnel reaches – the first time such inspection was ever conducted in an active wastewater tunnel. A special inspection pontoon was constructed by the contractor to carry two inspectors, lighting, tools, video and audio equipment and supplemental air supplies. During each inspection the pontoon was pulled upstream to the next lateral using a winch located in the lateral; fiber-optic cable was also pulled through to allow real-time video and audio of the inspection. Video and audio communications were maintained continuously between inspectors, above-ground crews and the engineer.
The inspection was completed on schedule and under budget, and its objectives met and even exceeded. The resulting photos, videos and physical tests dramatically demonstrate the actual condition of the shafts, laterals and the tunnel itself, showing the nature, extent and the exact location of corrosion that will require future attention.
Completed with a perfect safety record, the required information was collected and will provide the documentation needed for the design of eventual rehabilitations. In the end, the city obtained certainty over the condition of the tunnel, its continued service and the exact repairs that must be made to ensure a long and successful life.
About the Authors:
Clint Walker, P.E., is a Vice President in the Austin office of national environmental engineering and consulting firm Malcolm Pirnie, Inc. With more than 19 years of experience in the water industry, he specializes in the planning, design and construction of water, wastewater and recycled water projects throughout the Southwestern United States. L.R. "Randy" Pohren, P.E., was the Lead Project Engineer for the City of Austin. He currently serves in the Facility Engineering Division of the Austin Water Utility. He has over 25 years of experience in the design and construction of major wastewater process and treatment facilities.