Seattle Design/Build Project Helps Lower Costs

June 1, 1999
One example of a public/private partnership process is the Seattle Public Utilities Tolt River Water Treatment Plant project. SPU and a team headed by R.W. Beck and Malcolm Pirnie went through what was one of the of the largest alternative procurement efforts in the country at the time.

One example of a public/private partnership process is the Seattle Public Utilities Tolt River Water Treatment Plant project. SPU and a team headed by R.W. Beck and Malcolm Pirnie went through what was one of the of the largest alternative procurement efforts in the country at the time.

SPU planned to develop a new 120 mgd water treatment plant incorporating filtration/ozonation for a surface water supply on the Tolt River. Utility staff initially benchmarked the cost of the project using a traditional or conventional approach. SPU then went through an extensive design/build/operate, or DBO, procurement process, through which private contractors bid the design and construction of the facility, as well as a contract for the operation of the facility for 25 years. SPU retained ownership and liability for future capital improvements. The City of Seattle provided project financing.

SPU negotiated a contract with a consortium lead by CDM-Phillips that resulted in a cost-savings of 40 percent or $70 million less than what SPU would have expected for a similar facility developed and operated using the traditional approach. In addition to the dollar savings, SPU benefited from risk mitigation, rate stabilization and guarantees concerning regulatory compliance.

Last summer, the Seattle City Council approved SPUs recommendation to hire another team headed by R.W. Beck and Malcolm Pirnie to help determine the best contracting process for several facilities on the Cedar River.

The Cedar River is a larger, more complex system than the Tolt, and the projects include a 250 mgd treatment facility with associated water transmission and storage facilities; the upgrade and rehabilitation of an existing diversion facility; and a salmon hatchery and series of fish passage structures. The team is now in the early stages of exploring the possibilities of alternative arrangements for water treatment, headworks rehabilitation and fish passage work.

SPU initially needed to develop new water treatment plants for a sizable source of water supply. Utility staff benchmarked the cost of the projects using a traditional or conventional approach. However, because SPU wanted to provide the most cost-effective approach and did not have staff available for operating complex treatment plants, the city concluded that the DBO process was more promising than a traditional approach.

They were persuaded by the potential for substantial construction and operating cost savings created by efficiency and quality improvements resulting from designers, constructors, and operators working together as a team from the beginning of the projects.

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track