Construction of the recycled water pump station.
Click here to enlarge image“With a DBO team you have a design engineer and a contractor familiar with building treatment plants, and an operator familiar with operating it,” said Bert Rapp, city Public Works Director. “That gives us the best combination with three parties at the design table, the construction site, and finally in the operation of the plant. The DBO team we selected gives us the most economical method and the highest value in building the treatment plant.”
Substantial cost savings have come from using a design-build open-book model. The project team used an itemized list of cost items that was open to all members of the DBO team. All four parties (city, American Water, W.M. Lyles, and Kennedy/Jenks Consultants) were looking for more efficient ways to complete the project without sacrificing the overall quality. DBO project delivery along with the open-book model helped all parties understand the cost implications (positive and negative) of design decisions as the process moved forward.
Design Elements
A unique plant feature is the ability to “peak-shave” electrical use during the hours when power usage is highest. The price for power is highest between noon and 6 p.m. Since the typical peak flow of wastewater comes in at 9 a.m., the plant normally treats the most flow when electrical prices are highest. Processes like aeration and UV disinfection use substantial amounts of power. The flow-equalization system at the beginning of the treatment process was designed to “shave” (remove) the extreme peaks by day and the deep lows at night. Peak shaving allows the city to minimize flow during the day and to meter the wastewater back into the plant for treatment when power demand (and cost) is lower.
The daily flow rate to the plant is estimated to vary between 0.40 mgd to 6 mgd and this flow range would be equalized to roughly 2 mgd throughout the day. During a storm event, the flow-equalization system is designed to equalize the peak flow from 9.0 mgd to 6.0 mgd.
The new plant will use a biological nutrient removal (BNR) membrane process to remove nitrogen from the incoming wastewater.