Long distance heating pipe installation

Feb. 15, 2009
The company E.ON Westfalen Weser Energie-Service GmbH, Kirchlengern, had the task of building a biogas plant in the lower Saxon region of Hessisch Oldendorf in Germany for a town with approximately 20,000 inhabitants on the Weser River. The plant will produce 11 million kilowatt hours of power annually; 13,000 t of corn and 3,000 t crop, as well as liquid manure, lopping and kitchen waste are required each year...

June 2008 -- The company E.ON Westfalen Weser Energie-Service GmbH, Kirchlengern, had the task of building a biogas plant in the lower Saxon region of Hessisch Oldendorf in Germany for a town with approximately 20,000 inhabitants on the Weser River. The plant will produce 11 million kilowatt hours of power annually; 13,000 t of corn and 3,000 t crop, as well as liquid manure, lopping and kitchen waste are required each year.

The waste heat caused by the power production is intended to be fed into a long distance heating network. The warmed up water will reach the end consumer at a temperature of approximately 70°C and flows back to the biogas plant at approximately 40°C. Powerful pumps keep the water circuit flowing. On the way to the end consumer, any heat loss must be avoided. Therefore insulation and a network control are decisive factors for the pipe system to be installed.

Bonded outer pipes from the manufacturer Isoplus from Rosenheim were installed for the forward and reverse flow. Inside the 280 mm PE outer pipes the 168 mm OD medium pipes, made of steel, were bedded inside a hard foam layer to provide heat insulation. Control veins were integrated inside the insulation, which react to any leakages. The long distance heating pipes are suitable for operating temperatures of up to 155°C and an operating pressure of up to 25 bar.

About 2 km of the total 2.5 km bore length have already been installed from the biogas plant to the town with the open trench method. In compact areas it is virtually impossible to use this method.

Grundodrill bore rig during the pilot bore.This is the case in 2 sections in Hessisch Oldendorf over lengths of 192 m and 100 m. The installation in these areas are planned to be carried out with the HDD bore method. The very heavy traffic here was the main reason for choosing this method opposed to the open trenching method.

The bore path was placed behind the houses on a 3 to 4 m wide public strip with a water guiding mill trench. A distance of 2 m is kept between both long distance heating pipes for the forward and reverse flow.

The bore path at the rear of the houses.E.ON contacted the local company Friedrich Meier to carry out the installation. The civil and underground engineering company has almost 16 years experience with the HDD bore technology. The brand new system Grundodrill 15N (Manufacturer: Tracto-Technik, Lennestadt) was chosen to carry out this task. The previous bore rig, type Grundodrill 12 G, had been successfully used for 10 years with over 7,000 operating hours and is now being applied in Kazakhstan.

The head of this project Lutz Homeier comments: "An advantage of the new Grundodrill 15 N is the fact hand written logging of the bore data is no longer necessary. This is automatically stored in a data logger. The detailed evaluation can be processed after the bore process on a computer back at the office."

The bore path was chosen to allow for a flat entry and exit angle, in order not to overstrain the bending stiffness of the heating cables too much. This provided a total bore length of 228 m. The effective bore length was 180 m.

Pipes for forward and reverse flow ready for installation.The installation depth was 1.30 m, even 1.80 m in some areas close to the mill trench, below the stream. The pilot bore took around 4.5 hours in the clayish mixed soil with pebbles and stony partitions. In the meantime the heating pipes, which were delivered in 16 m lengths, were welded together to form two pipe lengths each of 96 m, as there was insufficient space to lay out the total length of 192 m on the target side.

Initially the bore had to be expanded in 2 working processes to 385 mm and 485 mm diameter and cleaned, to ensure a faultless pipe installation. The pulling in process was carried out without any problems. After the installation of the first 96 m length there was a short interruption, so that the second pipe length could be welded on. After 4 hours, which were required for the welding, x-raying and subsequent insulation of the connection seams, the rest of the pipe was then pulled in. The total pipe weight was guessed at 7 t, but the maximal pulling force was only 3 t. The complete project, including the parallel bore and the other section with 2 bores each over 100 m each were completed after 12 working days.

First of all the long distance heating will be provided to the town hall, the school and the hospital, but many private consumers are already showing interest. The next step will be to connect public access outlets. The supply of long distance heating is available from April 2008 onwards.

###

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track