Renovating drainage infrastructure beneath historical Bucharest
BUCHAREST, Romania, Nov. 19, 2007 -- Insituform Technologies Ltd. of the UK (ITL) has a 30-year history of high quality GRP liner installations. ITL has the capacity to install GRP liners from as little as 600 mm diameter (or 750 mm x 500 mm in egg-shaped sewers) up to as large as 2,000 mm diameter (or 2,000 mm x 1,500 mm in egg-shaped sewers). The company can also install special bespoke shapes upon request.
ITL in early 2007 established a branch office in Romania and since then ITL has been involved in some major GRP lining works across the country. Based on ITL's early successes, in mid 2007 Insituform Balcani s.r.l. was formed in Romania.
Romania is a country on the eastern fringes, and in 2007 became one of the newest members, of the European Union (EU). It is country that has had what might be conservatively termed a very 'colorful' history. From revolution to constitutional monarchy and from communism to democratic EU membership, it is a country that, in its time, has seen many great changes.
Throughout this history the country, and in particular its capital Bucharest, has been able to boast some of the finest architecture in Europe. However, the advent of the communist state for most of the latter half of the 20th century meant that much of its best architecture was flattened to make way for 'modern' buildings. Fortunately this was not the case in the historic centre of Bucharest, which seemed to have missed the worst of the ravages of the communist rebuilding program, and so retains much of its historical architecture and picturesque narrow streets.
Since joining the EU the Romanian economy has been boosted by over €9 billion of foreign investment and this has allowed some major reconstruction works to be undertaken.
Bucharest is the main political and administrative centre of the country, being the residency of the Presidency, the Parliament, and the Government, as well as the headquarters of many political parties, cultural and educational institutions, financial and commercial institutions and banks.
For the historic centre of Bucharest, being ignored in the communist rebuilding program has been both a blessing and a curse in that, whilst having been passed by during the building programs, much of it has fallen into disrepair, including large sections of its drainage system.
As part of a major restoration scheme for the historic centre of Bucharest, the local authorities of the City of Bucharest have introduced a project known as the 'Refurbishment of Roads and Utilities within the Pilot Area "A" of the Historic Zone Bucharest'. This project, which commenced in October 2006 and runs to April 2008, with the potential for subsequent further work. The current phase of the works is valued at some €20.7 million and includes a requirement to renovate certain sections of the historic centre of Bucharest's sewer network.
The works are being funded by a €1.8 million grant from the Dutch Government, €8 million EU funds administrated by EBRD and €10.9 million from the budget of Bucharest City Hall.
The project is being managed for the City Authorities by General Contractor Sedesa Constructions and Services Rom S.R.L. on behalf of Sedesa Obras y Servicios S.A. of Spain (Sedesa).
Sedesa is an established business group with more than 60 years experience and international operations. Building on this background, the company is currently in the midst of a major strategic plan, which has involved significant international expansion. Today, Sedesa boasts a solid presence in several European countries, whilst continuing to enter new markets on a global scale.
The company has a leading reputation in each of its business areas: Construction, Real Estate, Environment, Energy and Franchising. The wide range of personalized services and provisions offered by each sector ensures that the group remains at the forefront in all of its activities.
Sewer Renovation
In terms of the sewer works, a tender was drawn up in which ITL was named as the renovation subcontractor. ITL was chosen due to its extensive experience in the sewer renovation market worldwide, which it has established on a vast variety of projects over the past 30 years, and the availability it offered in terms of the variety of trenchless or 'No-Dig' renovation systems it utilizes.
ITL, through its branch office in Romania, won the contract, valued at approximately €3 million, to complete the work in Bucharest, which included initial cleaning and CCTV inspection of some 3,000 m of the existing sewer network. Subsequent to this preliminary work, ITL was required to develop a full and detailed construction design of the proposed renovation scheme that would be required to completely refurbish the surveyed sections of sewer.
With completion of the planning stages, the project ultimately required the use of both GRP segmental lining and CIPP lining for the rehabilitation of the mainline sewers lengths; Internal Rehabilitation of the existing manholes using grout injection techniques over a surface area of some 2,037 m2; Lining of the lateral services connecting to the mainline sewers using CIPP techniques (a total of some 1,200 m in length) and a final CCTV survey and report of the completed works. In total the project duration was expected to be 370 days. There was also the possibility that subsequently the project could be extended to include further sewer lengths.
ITL commenced work on the project with the cleaning and CCTV survey program. This was followed by the engineering design work.
In April 2007, ITL started the GRP installations for the rehabilitation of an egg-shape pipe in Gabroveni Street. This 225 m length was completed on 31 May. Installation continued with a GRP 50 m lining in an egg-shape sewer beneath Selari Street (Section 2), which was completed on 25 June. In July work started in another egg-shape pipe beneath Lipscani Street (Section 1). This 205 m length was completed on 27 August. In early September the next stage of the project started with the GRP lining of an egg-shape sewer beneath Franceza Street. At the time of writing this 314 m long section had also been completed.
GRP Lining
GRP lining is classed as a segmental lining system. This means that it utilizes preformed/prefabricated liner sections as the basis of the lining system. A GRP or glass-reinforced-plastic liner is essentially a fiber-glass/resin product which is factory manufactured and moulded to the precise size and shape of the pipeline it is designed to rehabilitate. The design is normally based on the minimum dimension permissible within the deteriorated pipeline under repair. This ensures that the liner can be installed throughout the pipe length without any deformation in the host pipe preventing access. GRP liners can be also utilized to negotiate bends in pipes by utilizing short length liner pipes.
As the GRP liner segments are preformed to the minimum dimension of the host sewer, their installation is normally achieved manually with specially fabricated end profiles which allow the segments to knit together closely to ultimately form the completed lining length. Within the sewer, the liner segments are positioned using spacer blocks to create the lining, with an annulus between the liner outer wall and the pipe inner wall. Normally this annulus is grout filled as the lining construction advances. This provides the necessary bond between the host pipe and the new liner and adds to the structural integrity of the completed system.
For the Bucharest project, the GRP liner segments have been manufactured by Stanton-Bonna in the UK and shipped to Romania by road transport.
Once a lining length is completed, the pre-surveyed positions of any laterals are reopened to re-make the connection.
It is only once the main GRP sewer lining is completed that the lateral connections are renovated. The CIPP lining installations for these laterals is undertaken from within the main sewer. Subsequent to each lateral lining, the main/lateral connection is sealed completely using the new extended lateral connection repair connection seal, which ITL has recently developed in conjunction with lining product specialist Trelleborg-epros.
Other Works
In other works the mainline sewer CIPP linings on the project will comprise some 1,711 m in length and will utilize the Insituform® Process lining technique using water inversion/hot water curing techniques.
Lateral connection linings for these sections will be undertaken once CIPP work has been completed and the lateral connections have been remade into the mainline sewers. Sealing of the connections will be completed again using the new lateral connection repair seals.
Commenting on the works for Bucharest City Authorities, Catalin Cazacu, Architect and Contract Representative said: "On the occasion of the 'Bucharest Days', organized by the City Hall of Bucharest, and which took place in September to celebrate Bucharest's 548 years of documented history, areas benefiting from the 'Refurbishment of Roads and Utilities within the Pilot Area "A" of the Historic Zone Bucharest' project, Smârdan and Lipscani Streets in the Historical Centre, were opened and played host to the 'Le Arti per Via' show which involved traders in the street and Italian artisans dating back more than 100 years." He went on to say: "We are going through a period of repositioning for the parties involved with the work, as the diversity and the complexity of the project has been modified, and the position of the Capital City towards this project must certainly be reviewed. Urban furniture items, such as benches, light pillars, advertisement posters, signs, flower baskets and verdure spots would be introduced. The streets would have urban perspectives and personalized pavements which should evoke both their historical importance and urban usefulness."
For the General Contractor, Sedesa Constructions and Services Rom S.R.L., Bogdan Mocanu, Project Manager and Contract Representative, said: "The project "Refurbishment of Roads and Utilities within the Pilot Area "A" of the Historic Zone Bucharest" is the first high quality project, in comparison with the other projects from Romanian historical cities like Sibiu and Sighişoara, which has aimed for the reinforcement of the urban architecture and of the streets, not the refurbishment and the modernization of the utilities. It is an animated project which modifies and adapts the final purpose, depending on the archaeological discoveries, using technical solutions for saving and protecting the city. So, maintaining the unique Romanian character remains the main challenge for the beneficiary, the general contractor and subcontractors."
ITL also recently won a major GRP installation contract with Thames Water in the UK for lining work on the Crossness sewerage treatment plant. The contract is valued at over £1 million and comprises the installation of GRP liners of 1,400 mm diameter, 945 mm x 1,400 mm ovoid and 2,000 mm x 1,370 mm ovoid cross-section over a total length of some 1,000 m. The contract also includes the renovation of 13 access shafts including new ladders and landings. This work is due to start in October 2007.
Insituform®, Insituform Technologies® and the Insituform® Logo are registered trademarks of Insituform Technologies Inc. and its affiliates in the UK and other countries.
###