Black & Veatch uses trenchless technology for water main rehabilitation in Hong Kong

Aug. 24, 2009
HONG KONG SAR, Aug. 24, 2009 -- Black & Veatch has completed the rehabilitation of the first of five water mains that lie beneath the heavily trafficked Lion Rock Tunnel in Hong Kong Special Administrative Region...

HONG KONG SAR, Aug. 24, 2009 -- Black & Veatch has completed the rehabilitation of the first of five water mains that lie beneath the heavily trafficked Lion Rock Tunnel in Hong Kong Special Administrative Region. The company is using innovative trenchless technology for the Lion Rock water mains to reduce impacts to commuters.

"One of the major constraints on this project was getting access to the mains," said Alan Man, Black & Veatch Vice President and leader of the company's water business in Hong Kong SAR. "Access to the pipe gallery via the shafts within the tunnel is permitted for only 14 days a month and then only between 1:30 am and 6:00 am."

The Lion Rock Tunnel is a vital component of Route 1 that connects Sha Tin in the New Territories and Kowloon. The five water mains that lie beneath the carriageway of the Lion Rock tunnel transfer treated water from the Shatin Water Treatment Works, the largest water treatment facility in Hong Kong, to the heavily populated areas of Kowloon and Hong Kong Island. The mains, which were built in the 1960s and '70s, are approximately 1.4 kilometers (km) in length and range from 1.2 meters to 1.5 meters in diameter.

The lining process that Black & Veatch used involved an initial tack coat of epoxy being applied to the host pipe, which improves the bond with the FRP lining."Major excavation of the carriageway was not allowed and replacement was not possible," said Man. "As conventional rehabilitation techniques such as slip lining were also not feasible, we had to use innovative in-situ methods within the pipe to get the job done."

Black & Veatch adopted the use of hand-applied fiber-reinforced plastic (FRP) for the rehabilitation of the mains. Various trials and demonstrations on the FRP system were carried out on site. Relining of the first main was completed by mid-December 2008 at an average rate of approximately 25-40 meters per day. Final inspections and pressure tests were completed and the first water main was re-commissioned in March 2009.

Work has now commenced on two other mains with all five mains targeted to be completed in early 2011.

"The Lion Rock Tunnel water mains are an essential component of Hong Kong's water supply network," said Man. "By using innovative technology, we are able to successfully rehabilitate these mains with minimal disruption to commuters who rely on the use of the tunnel every day."

Hong Kong's Water Supplies Department launched the Replacement and Rehabilitation Programme of Water Mains, one of the largest pipeline rehabilitation programs in the world, in 2000. The program aims to rehabilitate or replace a total of 3,000km of water mains by 2015, at an estimated cost of HK$ 19.2 billion (US$ 2.5 billion), improving the condition and reliability of Hong Kong's water supply network.

Black & Veatch is responsible for replacing or rehabilitating approximately one-third of the pipelines in the overall program, and is involved in Stages 1, 2 and 4.

About Black & Veatch
Black & Veatch is a leading global engineering, consulting and construction company specializing in infrastructure development in energy, water, telecommunications, management consulting, federal and environmental markets. Founded in 1915, Black & Veatch develops tailored infrastructure solutions that meet clients' needs and provide sustainable benefits. Solutions are provided from the broad line of service expertise available within Black & Veatch, including conceptual and preliminary engineering services, engineering design, procurement, construction, financial management, asset management, program management, construction management, environmental, security design and consulting, management consulting and infrastructure planning. With US$3.2 billion in revenue, the employee-owned company has more than 100 offices worldwide and has completed projects in more than 100 countries on six continents.

Black & Veatch's global water business provides innovative, technology-based solutions to utilities, governments and industries worldwide. Local project teams work with multinational water and wastewater treatment process experts to address site-specific challenges through a broad range of consulting, study, planning, design, design-build and construction management services. The company's Web site address is www.bv.com.

###

Sponsored Recommendations

WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track

Automated Fresh Water Treatment

March 15, 2024
SCADA, Automation and Control for Efficient and Compliant Operations

Digital Transformation Enables Smart Water

March 15, 2024
During this webinar we will discuss factors driving the transformation to digital water, water industry trends, followed by a summary of solutions (products & services) available...

Smart Water Solutions: Transforming the Water Universe

March 15, 2024
Water is our most valuable resource, and efficient and effective water and wastewater handling is crucial for municipalities. As industry experts, you face a number of challenges...