Open ocean retrieval of microtunnelling machine. Photo by URS Corporation Click here to enlarge imageRight from the start it was clear that the design of an outfall extension for the wastewater treatment plant at Fort Kamehameha, off the coast of Hawaii, would present unique challenges. The project required construction of a new 3.9-km-long ocean outfall beneath coral reefs and environmentally sensitive ocean floor. The unprecedented combination of overwater shaft construction and underwater microtunnelling were employed to complete the project.
A total of 3,900 m of pipeline will be installed throughout the project. About 2,510 m of high-density polyethylene (HDPE) pipe was installed by open trenching over a submerged shallow reef at elevations of -0.5m to -1.5m. Microtunnelling was used to install approximately 800 m of reinforced concrete pipe at seven to 10 m beneath the reef flat and sidewall of the entrance channel to Pearl Harbor. The deeper portion of the outfall is in the final phase of construction and entails installing 2,164 m of HDPE pipe at an elevation of -46 m in the Pacific Ocean off the south end of the Honolulu International Airport reef runway.
Geotechnical site characterisation included overwater drilling and sampling and marine geophysical surveys. The microtunnelling alignment that was selected avoided thick deposits (more than 50 m) of loose, liquefiable sands. Two 400-m-long microtunnel drives, one jacking shaft, and two underwater retrieval pits were constructed in open ocean waters over six metres deep, with the microtunnelling shaft bottom at 12 m below sea level.
Six overwater borings explored the microtunnel portion of the alignment. The borings were drilled to elevations ranging from -10 m to -27 m, using a SIMCO drill rig mounted on a pontoon for the shallow reef flat borings. For the borings in deeper water, a large barge and truck-mounted Mobile B-53 was used.
During field exploration, wave conditions and tidal fluctuations influenced drilling progress, particularly over the shallow reef flat, where large breaking waves repeatedly interrupted drilling. Laboratory tests for microtunnelling and shaft construction included: classification and index tests, specific gravity, unconfined compression, triaxial compression, hardness, and petrographic examination.
The microtunnel alignment was selected to avert crossing through a 300-m-wide erosional channel infilled by soft silt and loose sand to more than 50 m below the ocean floor. The geotechnical analysis had indicated that the silt and sand were in a liquefied state.
Subsurface conditions along the microtunnel alignment required microtunnelling through full-faced and mixed-face conditions consisting of saturated lagoon deposits and coralline deposits, including beach sand and coral reef rock (limestone). Approximately 85% of the alignment consisted of loose silty sand and gravel, soft sandy silt, layers of hard cemented coral reef rock, and loose to dense sand and gravel with cobble- to boulder-sized coral chunks and clasts. The rest of the alignment consisted of a full face of hard coral reef.
The project required the construction of a watertight microtunnel jacking shaft with a full-perimeter excavation support system and either two watertight microtunnel receiving shafts or two underwater receiving excavations. The choice was a watertight jacking shaft using interlocking steel sheet pile walls with a groundwater and seawater bottom plug created by jet grout ground improvement. Open underwater pits were excavated for retrieval of the microtunnel-boring machine (MTBM) at the end of the two microtunnelling drives.
The open ocean microtunnel jacking shaft entailed a number of design, construction, and operational challenges, including:
• The open ocean shaft needed to withstand tidal fluctuations, wave forces, and storm surges throughout shaft construction, microtunneling, and pipe connection phases.
• Poor subsurface conditions created difficulties for sheet pile driving and installation of the jet grout groundwater and seawater bottom plug. To address that issue, the geotechnical report indicated that pre-drilled continuous, overlapping holes would be needed to properly install the excavation support system.