Mississippi pipeline boasts record installation of ductile iron pipe

May 16, 2012
Sixty feet below the surface of Sowashee Creek in east Mississippi lies a new section of pipeline -- 1,640 feet of 36-inch ductile iron pipe -- marking the longest length of this size ductile iron pipe ever installed using horizontal directional drilling...
BIRMINGHAM, AL, May 16, 2012 – Sixty feet below the surface of Sowashee Creek in east Mississippi lies a new section of pipeline -- 1,640 feet of 36-inch ductile iron pipe -- installed with little more than a ripple’s impact on the waterway. This section of pipeline marks the longest length of this size ductile iron pipe ever installed using horizontal directional drilling (HDD), a trenchless method of pipe installation that minimizes surface disturbance.

The record “pull” is one of four HDD installations completed as part of a 32-mile ductile iron pipeline that will carry treated wastewater from Meridian, Miss., to a new industrial facility northeast of the city. The three shorter pulls were 1,000 feet, 880 feet and 880 feet.

Since 1996, HDD has grown in popularity as an alternative method of pipe installation.

“Our customers use HDD in situations where open cut trenches are not desirable, for instance under waterways, roadways, congested areas or environmentally sensitive areas,” said Ralph Carpenter, project manager with American Ductile Iron Pipe, a division of American Cast Iron Pipe Company, in Birmingham, Ala.

With HDD, a gentle arcing pathway, called a bore path, is drilled underneath an object or area. Then, a tool called a reamer is used to enlarge the bore path greater than the diameter of the pipe being installed. This can take several passes, enlarging several inches at a time. Finally, the pipe is pulled through, completing the process.

During the design phase, engineers estimate the pullback force required to pull the pipe back through the bore path.

“The allowable pull load for these four sections of pipe was 310,000 pounds,” Carpenter said. “One pull, through an old landfill area, tested our calculations, nearly reaching the allowable limit. With the other three pulls, the applied loads were less than half the allowable limit.”

Layne Heavy Civil, Fairborn, Ga., the general contractor for the project, and subcontractor REM Directional, Boligee, Ala., were responsible for pipe assembly and drilling the bore path.

“Contractors preassembled two standard 20-foot sections of pipe above ground, making multiple 40-foot sections, and staged them near where the pipe would enter the bore path,” Carpenter said. “This was a novel approach that saved a considerable amount of time.”

Ductile iron was selected as the pipe material for this project early on due, in part, to its strength and reliability.

“This pipeline, when complete, will span some 30-plus miles, which means fairly high water pressures; this is a job for ductile iron pipe,” Carpenter said.

From pre-design to completion, the record-breaking pull was a team effort, Carpenter said.

“This project is a prime example of the advantages of ductile iron pipe, HDD installation and American’s knowledge and experience with HDD technology,” he said.

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track