Vermont wastewater treatment facility to generate its own heat and power from digester gas

March 6, 2003
A wastewater treatment facility in Vermont has selected Northern Power Systems to build an on-site power system that will burn methane gas to generate electricity and heat for the facility.

WAITSFIELD, Vt., March 6, 2003 -- The Essex Junction Wastewater Treatment facility in Essex Junction, Vermont has selected Northern Power Systems to engineer, build and install a $245,000 on-site power system that will burn methane gas produced by wastewater processing to generate electricity and heat for the facility.

The new cogeneration system will produce over 400,000 kWh of electrical output per year, equivalent to 41% of the facility's current annual demand. At the same time, the system will reduce the plant's CO2 emissions by over 500,000 pounds--the equivalent of eliminating 42 cars from the road per year.

As part of its commitment to removing financing obstacles to such environmentally sound systems, Northern helped the Essex Junction facility obtain grant and rebate assistance for the project from various outside sources.


The Essex Junction Wastewater Treatment system will employ a new controls method -- the first of its kind for use in a biogas cogeneration application--developed by Northern Power Systems for the project. The controls method will enable the facility to conduct peak shaving (reducing metered demand by boosting output kW during short, higher demand times) while monitoring the power and heat requirements of the site. The system is expected to yield a total annual electric utility savings of about $30,000.

New system will boost efficiency with microturbines
The Essex Junction Wastewater Treatment facility processes approximately 1.7 million gallons of wastewater per day from the suburban Burlington communities of Essex Junction, Essex and Williston. The facility also runs a biogas anaerobic digester plant which produces 56,500 therms of methane gas per year.

The plant flares 45% of this methane gas and burns the other 55% in a boiler to heat the digester tanks, accelerate decomposition of the solid waste, and kill off pathogens in the process biosolids. The new system will dramatically increase efficiencies by employing microturbines to burn 99.8% of the methane gas, a design that will eliminate the need to flare the previously unused portion. The electricity produced will power pumps, grinders and other process equipment.

Environmental benefits and cost savings
The Essex Junction plant will realize significant environmental benefits and energy cost savings by blending the methane with natural gas, which also serves as a back-up gas source in the event of digester maintenance or interruption of biogas supply. Modulating the mix allows the microturbines to conduct peak shaving to a greater extent than if running on methane alone, automatically increasing the output of the microturbines to meet the additional electrical needs. Blending also improves the reliability of the system by stabilizing the fuel input into the turbines.

Through cogeneration, the recovered heat from the turbines will be used to heat the digester tanks and will offset 100% of the need to run a boiler for this same purpose.

Broad appeal to similar wastewater treatment facilities
According to Dan Reicher, executive vice president of Northern Power Systems and former U.S. Assistant Secretary of Energy, the system developed with the Essex Junction facility has widespread applicability nationwide. Reicher, who led a $1.2 billion program to advance energy efficiency, renewable energy and distributed generation, said, "An EPA Clean Water Needs Survey indicates that there are some 3,300 wastewater treatment facilities similar to the Essex Junction plant in the United States. From delivering basic electricity, to cost reductions and reduced environmental impact, this type of system design delivers terrific value for anaerobic digestion wastewater treatment facilities," he added.

The average cost per kWh produced by the system will be 2.46 cents (including annual maintenance expenses), yielding a 6.37-cent savings when compared to the current utility rate. In addition to the energy savings, peak shaving will accrue $4,500 in savings, thereby yielding a total annual electric utility savings of about $30,000.

Based on a national utility average of 1.3 pounds of CO2 emissions per kWh generated, the cogeneration system will offset over half a million pounds of CO2 emissions per year (the equivalent of removing approximately 42 cars from the road per year).

"We are confident that this system will deliver real environmental benefits and drive down electric consumption costs for local ratepayers," said James Jutras, Director of the Essex Junction Wastewater Treatment facility. "It's a real example of a win-win situation because we're able to share the benefits with our customers and the surrounding communities," he added.

Funding support from several sources
Efficiency Vermont, Vermont's energy efficiency utility, committed $40,000 toward the cost of the cogeneration project and provided extensive assistance to Essex Junction to help move the project forward by leveraging additional resources and offering technical recommendations. NativeEnergy, a Vermont-based renewable energy company that supports the development of new renewable energy sources, provided significant additional financial support through its up-front purchase of the "renewable energy credits" the project will generate. The project was also supported by the Biomass Energy Resource Center, an independent, non-profit organization in Montpelier, Vermont, that assists in the development of sustainable biomass energy projects across the U.S. and around the world.

About Northern Power Systems
Northern Power Systems designs, builds and installs ultra-reliable electric power system solutions for industrial, commercial and government customers worldwide. Since the company's founding in 1974, Northern has installed over 800 systems in 40 countries on all seven continents. For more information, visit Northern on the web at www.northernpower.com.

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track