Arlington modernizes Pierce-Burch Water Treatment Plant for long-term reliability

The Pierce-Burch plant overhaul involves replacing outdated infrastructure, expanding capacity and integrating advanced automation and power systems, all while managing land-use constraints and maintaining continuous operation during construction.
Feb. 5, 2026
4 min read

Key Highlights

  • The project includes new clearwells, wash water recycle facilities, a chemical feed building, and upgraded electrical and pump stations to enhance operational capacity and resilience.
  • Construction is phased to maintain continuous plant operation, with careful sequencing to minimize disruptions during peak demand periods.
  • Coordination with city departments, regulatory agencies, and utility partners has been critical to managing land constraints and complex construction logistics.

The Pierce Burch plant’s original design had only one electrical feed to the site, which would cause a shutdown if anything were to happen to that single line

- Arlington Water Utilities Senior Engineer Dylan Rumble, P.E.

Operational constraints added another layer of complexity. Historically, Pierce-Burch operated seasonally, shutting down during winter months while Arlington’s newer John F. Kubala Water Treatment Plant carried the load. The project team had to carefully sequence construction to keep Pierce-Burch online during peak summer demand, while still carving out shutdown windows for tie-ins and testing.

A phased construction approach proved essential. Early phases rerouted wash water to the city’s sanitary sewer system, allowing the demolition of failing wash water ponds and clearing space for a new wash water recycle basin and chemical building. Subsequent phases delivered two new 4-million-gallon clearwells—each nearly 200 feet in diameter—constructed on the footprint of the former ponds. Excavated material from 40 feet below grade was stockpiled on site to minimize truck traffic through surrounding neighborhoods.

“The Pierce Burch plant’s original design had only one electrical feed to the site, which would cause a shutdown if anything were to happen to that single line. When this project is complete, the plant will have two electrical feeder points and multiple generators, greatly reducing the chance that a power outage caused by extreme weather would lead to an interruption in water production,” said Arlington Water Utilities Senior Engineer Dylan Rumble, P.E., who leads the project team for the City.

Later phases added bulk chemical containment, a new pump station, stormwater retention ponds, and multiple electrical buildings housing switches, transformers, and generators. These upgrades enable permanent power feeds, greater redundancy, and enhanced automation through new SCADA integration. Commissioning and startup are scheduled to begin in August 2025, with final demolition of legacy clearwells and completion of stormwater facilities in early 2026.

Coordination has been a defining feature of the project. Arlington Water Utilities has worked closely with the Texas Commission on Environmental Quality, power provider Oncor, and multiple city departments, while HDR, Archer Western, and Freese & Nichols have managed design, construction, and oversight through frequent coordination meetings and site walkthroughs.

Leadership transitions during construction also shaped the project’s long-term vision. With new utility leadership in place, Arlington made the decision to operate Pierce-Burch year-round once improvements are complete. This shift supports growing wholesale demand, reduces wear from seasonal shutdowns, and provides a critical backup if the Kubala plant experiences an outage.

When finished, the upgraded Pierce-Burch facility will deliver far more than new concrete and steel. Direct pumping to both of Arlington’s primary pressure planes, three new emergency generators, dual electrical feeds, and modernized power distribution will significantly enhance system resilience—ensuring the plant remains a cornerstone of Arlington’s water supply well into the future.

2025 Top Projects

WaterWorld has revealed the winners of its 2025 Top Projects Awards, honoring outstanding drinking water projects completed or in progress between Jan 2024 and July 2025. The ...
APU
Brookhurst PFAS treatment plant
Facing unprecedented challenges from PFAS contamination, Anaheim adopted a phased, collaborative approach utilizing ion exchange technology, operator training, and community outreach...
Missoula Water has launched a smart leak detection program using advanced acoustic sensors to identify underground leaks accurately, reducing water loss and minimizing community...
InPipe Energy
The HydroXS energy recovery system converts excess water pressure into renewable electricity at Skagit PUD’s reservoir site.
Skagit PUD's pioneering project captures pressure energy from its water system, converting it into clean electricity using micro-hydro technology, reducing emissions and supporting...
Phoenix Drone Pros
Signal Butte WTP expansion filter complex
The multi-phase project improves Mesa's water infrastructure by increasing treatment capacity, adding redundancies, and implementing innovative treatment technologies, ensuring...
City of Arlington
Pierce Burch Water Treatment Plant
The Pierce-Burch plant overhaul involves replacing outdated infrastructure, expanding capacity and integrating advanced automation and power systems, all while managing land-use...

About the Author

Alex Cossin

Associate Editor

Alex Cossin is the associate editor for Waterworld Magazine, Wastewater Digest and Stormwater Solutions, which compose the Endeavor Business Media Water Group. Cossin graduated from Kent State University in 2018 with a Bachelor of Science in Journalism. Cossin can be reached at [email protected].

Sign up for our eNewsletters
Get the latest news and updates